How do flexibility markets for Northern Powergrid work and how can I sign up my clients?

Thomas Hayes
Thomas Hayes
Founder & CEO, GridVolt

Quick answer

Your clients may be able to earn flexibility payments from their current or proposed commercial battery if they’re located in the Northern Powergrid area. We offer a way for installers to continue to earn money from their sites post-installation through flexibility and wholesale market services.

Your client’s commercial batteries may be able to take part in Northern Powergrid (NPg) flexibility markets and earn income from their setup

Northern Powergrid is in charge of the local electricity network across the North East, Yorkshire and northern Lincolnshire.

This knowledge base article is for installers in the region. If you’re quoting for a battery or battery-and-solar project, we can give you estimated income figures for the proposal. For clients who already have a battery, we can assess the installed equipment and estimate what it could earn from Northern Powergrid flexibility.

We’re GridVolt, a software provider whose Energy Manager plans battery charging and discharging around your client’s electricity needs for maximum financial benefit. Our GridTrade service allows your customers to take in these flexibility markets.

What would Northern Powergrid pay my client to do?

Connect your client through GridVolt and they could receive an income by:

  • Taking less electricity: We use the battery to power more of your client’s equipment when NPg needs lower demand locally. This reduces what the site takes from the grid.
  • Sending electricity back: The battery supplies more power than the site needs and sends the surplus to the grid, up to the maximum power the connection allows the site to send back.

NPg buys these services in particular parts of its network, known as zones. GridVolt arranges charging beforehand so your client’s battery has enough stored electricity to do the work required for payment.

At all times, we keep enough battery power and stored electricity for your client’s business, including what we’ve agreed to reserve for power cuts. We only offer what your client can actually spare, within the battery and inverter’s operating limits.

Can my client agree set times for Northern Powergrid to use their battery?

Yes, if those times match when NPg needs help locally. GridVolt tells NPg how much power your client’s battery can provide, when and at what price. If NPg accepts, we arrange for the battery to supply the site or send electricity back during those hours.

Your client is paid for doing that under NPg’s scheduled utilisation service.

For example, NPg’s November 2026 tender listed 6:30pm to 8:30pm every day in the Leeds–Royal Park Road zone, from 30 November to 6 December 2026. If your client’s site qualified, we could use their battery to power equipment during those two hours, reducing how much electricity they take from the grid.

Before making an offer, GridVolt checks that the battery can supply the power we’re offering for the full period and has enough stored electricity to do it. We’d only use it for this service during the hours in the accepted offer.

Can my client get paid to keep their battery ready, even if Northern Powergrid doesn’t use it?

Yes. NPg can pay your client to reserve a set amount of battery power during agreed hours. There can be a further payment when we use that power to supply the business or send electricity back to the grid. NPg calls this scheduled availability and operational utilisation.

For its monthly programme in high-voltage network zones, NPg gives us the following week’s instructions by the end of Thursday. These cover Monday to Sunday, and GridVolt has until noon on Friday to confirm we’ll follow them.

For example, your client might agree to reserve power from 4pm to 7:30pm. We protect enough battery power and stored electricity for that period, although the weekly instructions might require us to discharge it for only part of that time.

We turn down other trades if they would leave the battery short of what we’ve promised NPg.

Can my client offer their battery to Northern Powergrid for one month at a time?

Yes. During autumn and winter, NPg runs monthly tenders for flexibility needed the following month. NPg sets out the weeks, days and hours when it needs help. GridVolt can bid for the periods your client’s battery can cover, within each tender’s rules.

For high-voltage network zones, we offer to reserve battery power under NPg’s scheduled availability and operational utilisation service. If NPg accepts, it tells us a week ahead when it needs us to use that power.

In low-voltage zones, NPg buys scheduled utilisation. The hours when we’ll use the battery are agreed when NPg accepts the bid.

Could my client’s battery help while Northern Powergrid carries out network maintenance?

Potentially. It depends on where the site connects to NPg’s network and whether the battery and controls can provide the response needed for that work.

For its 2026 Tanfield tender in County Durham, NPg asked providers to respond with 15 minutes’ notice under its scheduled availability and operational utilisation service. That timetable is different from the week-ahead instructions in its current monthly programme.

Before putting your client’s battery forward, we review its connection and controls with you to establish whether it can do what NPg needs during the maintenance work. We can’t assume that from its ability to supply the building during a power cut.

How do I know whether my client’s battery is suitable for Northern Powergrid flexibility?

Send GridVolt these three details so we can assess the site and battery together.

  • The site’s postcode
  • The MPAN, or Meter Point Administration Number, from your client’s electricity bill
  • The battery and inverter make and model

We start with the network connection because NPg needs there to be flexibility in specific locations. The postcode is a start, but it won’t tell us alone if your client qualifies because nearby premises can connect to different parts of its network, so the postcode alone won’t tell us whether your client qualifies.

Having a low-voltage connection doesn’t mean your client can’t participate. On NPg’s November 2026 high-voltage competition documentation, they accepted equipment connected at 11 kV or below, including low-voltage sites in the relevant zones.

Our software works out what the battery can spare after covering the business’s own needs. A 50 kW inverter doesn’t mean all 50 kW is available for NPg. Your client may need some of that power to run equipment and want to keep some stored electricity for power cuts.

NPg’s minimum offer is 10 kW per zone. If your client can offer less, we may be able to combine their battery with others in the same zone. Together, we need to make sure the sites deliver the reduction in grid use or extra exports we offer.

The battery also needs enough charge to supply that power for the full time agreed. The November tender data lists a 30-minute minimum running time, but NPg may ask for longer. We confirm the duration before bidding. For example, we might agree to keep battery power ready from 4pm to 8pm. NPg could ask us to discharge it for just one hour within that period. We’d need enough charge to supply the power requested for that hour.

We can’t make solar panels produce extra electricity whenever NPg asks, so panels alone don’t qualify for these flexibility competitions. The difference is that a battery can store solar electricity until it’s needed and we can control when it discharges, although it must still meet NPg’s other requirements.

We also keep the whole site within its import and export limits. These set the maximum power your client is allowed to take from the grid or send back to it.

To measure what the site provides, NPg requires meter readings at least every half-hour. These must come from the grid connection and cover the whole site. GridVolt confirms that we can obtain them and that they meet NPg’s requirements for measuring the response.

Can I register a battery that I haven’t installed yet?

Yes. NPg can consider a battery you’re planning to install for its long-term tenders. It may set deadlines for installation and testing, so we’ll establish when your client’s battery would need to be ready.

For short-term tenders, the battery needs to be running and have a valid MPAN. Send us your expected installation and testing dates so we can identify which tenders you could include in the proposal. Northern Powergrid

NPg also introduced Flex Advance alongside its summer 2026 tender, offering some flexibility payments upfront for new equipment. That tender has closed. Ask us whether Flex Advance is available for your client’s project. We’ll confirm how much they could receive and what they’d have to provide in return before you include a payment in your figures.

How can I get my client into Northern Powergrid flexibility services?

Your client can take part in Northern Powergrid’s flexibility services directly or via an aggregator like GridVolt. Here’s how the two differ:.

Apply directly to Northern Powergrid flexibility services

Your client registers their company and equipment on Piclo, the platform NPg uses for its tenders. They must pass NPg’s company and technical checks and sign its flexibility services agreements.

NPg asks providers to sign two agreements, one with Northern Powergrid (Northeast) plc and one with Northern Powergrid (Yorkshire) plc. These set the main terms for participation. Each accepted offer then specifies the location, power and periods the provider must cover.

Once approved, your client would need to:

  • Prepare bids stating the power they can offer, the periods the battery can cover and the prices requested for the relevant service.
  • Receive and accept NPg’s instructions, then arrange for the battery to supply the agreed power for the full period.
  • Send the meter readings needed to measure the change in electricity taken from or sent to the grid.
  • Compare the payment statements with what they expected to earn and raise any queries.
  • Keep records of agreements, accepted offers, instructions and readings to support the payments claimed.

Managing this directly requires people who understand the trading process, software to control the battery and time to handle the administration.

Join Northern Powergrid flexibility services through an aggregator like GridVolt

You can ask GridVolt to handle this on behalf of your client and your company. We manage registration, bids, instructions, meter readings and payment paperwork as your client’s aggregator.

Our software coordinates batteries at different sites as a virtual power plant, or VPP. We combine only equipment that meets the location and service requirements for each NPg offer. Your client can use GridVolt even if their site reaches the 10 kW minimum on its own.

The battery stays right where it is at your client’s site. We send instructions through the controller to the inverter to manage charging and discharging remotely, and obtain the site’s meter readings so we can bill NPg.

Before your client joins, we confirm who they contract with, who submits offers, who provides the readings and how they get paid. We also confirm any ongoing payments to you based on trades, where agreed with GridVolt.

You install the battery, inverter and metering. We supply the controller and support you remotely while you test the installation and get it running.

How much could my client earn from Northern Powergrid flexibility?

We estimate earnings for each site separately. Your client’s payment depends on:

  • The service available where the site connects to NPg’s network.
  • How much battery power and stored electricity your client can spare after covering the business’s own needs, including backup.
  • The agreed price and how many of their offers NPg accepts.
  • The hours the battery must stay ready and how often NPg asks it to supply power.
  • Whether the site provides the full reduction in grid use or extra exports agreed with NPg.
  • The commissions agreed with your company and GridVolt.

NPg sets limits on the bid prices it will accept. For offers that include keeping power ready and supplying it, NPg considers both prices and how often it expects to need the power. It uses that calculation to compare bids. It doesn’t tell you what your client will earn over a year.

GridVolt estimates the income using the proposed or agreed prices, your client’s meter readings, electricity tariff and equipment limits. We also work out how taking part would affect their electricity bill.

For example, NPg might need the battery to discharge before an expensive evening period. If it can’t recharge in time, your client may have to buy more expensive electricity later to run the business. We compare the additional cost with NPg’s payment to see whether they would still be better off.

My client is in the Northern Powergrid area. What opportunities are there near them?

NPg’s November 2026 tender included these locations and service periods. They show the work your client’s battery could be offered for, subject to the site qualifying and meeting the bidding deadlines.

Location and network zoneWhat your client would offerDaily hoursService dates
Leeds (Royal Park Road)Supply power at set times.6:30pm to 8:30pm30 November to 6 December 2026
Crowle, near ScunthorpeKeep power ready. NPg confirms when to use it a week ahead.4pm to 8:30pm14 to 20 December 2026
Stocksbridge, Sheffield (Wheatacre Road)Keep power ready. NPg confirms when to use it a week ahead.4pm to 7:30pm14 to 27 December 2026

Source: NPg’s November 2026 tender specification and service-hours spreadsheet.

What about clients in other Northern Powergrid locations?

NPg expects to need help in the areas below, starting in the years shown. Those dates could change. Before you include income in the proposal, we’ll find out whether NPg is accepting offers and whether your client could take part.

Location and database zonePlanning year for local need
Wetherby (Audby Lane)2026
Harrogate (Starbeck)2026
Beal, near Knottingley2026
Hayton, near Pocklington2026
Kirkburn, near Driffield2026
Doncaster (Armthorpe)2028
Ripon2028
Whitley Bay (Monkseaton)2030
Middlesbrough (Prissick)2031
Ashington2032
Darlington (Darlington West)2032
Sheffield (Claywheels Lane)2033

Source: Northern Powergrid’s upcoming flexibility services planning data.

GridVolt follows NPg’s tenders as they’re published and considers other trading options for your client’s site.

What should I send GridVolt to check a client’s battery project?

Send GridVolt the site’s postcode, a recent electricity bill and the battery and inverter make and model. We can start with a proposed installation or a battery that’s already running.

For the full assessment, we’ll also need:

  • Twelve months of half-hourly import readings and export readings where available.
  • The current electricity tariff and any agreement for selling electricity back to the grid.
  • The battery’s continuous charging and discharging power in kW, the stored electricity it can actually use in kWh and any solar capacity.
  • The site’s import and export limits, plus any connection restrictions.
  • The power and stored electricity your client needs to keep for backup or other site uses.

Send a drawing showing how the site’s electrical equipment connects together and details of the existing controller and meter if you have them. You don’t need every item before you get in touch.

We’ll assess the equipment and model the savings and confirmed trading options for that site. You get figures to use in your proposal, and you keep the installation work and client relationship.

Northern Powergrid flexibility: installer FAQs

Does Northern Powergrid’s G99 approval also qualify my client for flexibility payments?

No. G99 approval is permission to connect the equipment to the grid. NPg must also check that the site and equipment qualify for flexibility, then accept an offer for the work. Explain these separate steps to your client before including flexibility income in the proposal.

Will my client need to change electricity supplier for Northern Powergrid flexibility?

No. Your client can keep their current supplier when they use GridVolt. Ask them for their supply, export and existing trading agreements so we can check whether another company already has rights to control the battery or use it during particular hours.

How will Northern Powergrid check how much flexibility my client’s battery provided?

NPg compares meter readings with a baseline: the power it assumes the site would take from or send to the grid without the flexibility work. Its November 2026 specification assumes 0 kW for generation and storage, a zero baseline. GridVolt checks how that applies to your client’s installation before you quote spare battery power or income.

Can I assume Northern Powergrid payments will continue for the battery’s lifetime?

No. The main agreement can remain in place, but NPg awards work for particular dates and hours. In your proposal, show income from an accepted contract separately from estimates for later years. NPg’s forecast of a future network need doesn’t promise payments to your client.

What is Northern Powergrid’s scheduled utilisation service?

Northern Powergrid’s scheduled utilisation service is an agreement for a site to take less electricity from the grid or send more back during hours set in advance. Your client’s battery could supply their equipment to reduce grid electricity use. NPg pays for what the site provides. The battery needs enough power and stored electricity for the full period.

What is Northern Powergrid’s scheduled availability and operational utilisation service?

Under Northern Powergrid’s scheduled availability and operational utilisation service, NPg pays for keeping power ready and doing the work requested. In monthly tenders for high-voltage zones, NPg confirms the following week’s work on Thursday. Separate maintenance contracts can give different notice. Your client must keep enough battery power and stored electricity for the hours they’ve offered.

What are Northern Powergrid’s month-ahead flexibility tenders?

Northern Powergrid’s month-ahead tenders are autumn and winter competitions for the following month’s flexibility. NPg publishes the locations and hours it needs. Under its November 2026 programme, NPg pays for keeping power ready and doing work in high-voltage zones. In low-voltage zones, it pays for scheduled work. Providers offer the periods their equipment can cover.