How do flexibility markets for UK Power Networks work and how can I sign up my clients?

Thomas Hayes
Thomas Hayes
Founder & CEO, GridVolt

Quick answer

Your clients may be able to earn flexibility payments from their current or proposed commercial battery in the UK Power Networks (UKPN) area. Contact GridVolt to check the suitability of their site and equipment, find out which trading options are open to them, and include trading opportunities in your battery (or battery + solar) proposal.

Your clients may be able to earn flexibility payments from their current or proposed commercial battery in the UK Power Networks (UKPN) area. Contact GridVolt to check the suitability of their site and equipment, find out which trading options are open to them, and include trading opportunities in your battery (or battery + solar) proposal.

GridVolt is an aggregator with a virtual power plant capability. We add proprietary software and an on-site controller to compatible equipment at the client’s site. Our Energy Manager plans charging and discharging around your client’s electricity needs, while GridTrade handles trading through the markets available for that site.

We offer a way for installers to continue to earn money from their sites post-installation through flexibility and wholesale market services. To find out more, please get in touch via our contact us page.

What would UK Power Networks pay my client to do?

Connect your client up via GridVolt and they could receive an income by:

  • Taking less electricity: Using power from the battery to supply more of the electricity needed at their site at agreed times, so they take less from the grid.
  • Send electricity back: Exporting electricity to the grid when UKPN needs extra supply in that area.
  • Charge the battery: Taking more electricity from the grid when UKPN needs more local use, such as when nearby solar or wind generation is high.

UK Power Networks buys these local flexibility services in:

  • Specific parts of London
  • The South East of England
  • The East of England

GridVolt keeps back the battery power and stored electricity your client needs for their site, including the agreed backup reserve. We only use what’s left for flexibility, within the equipment’s operating limits.

In other words, you can assure your client that we won’t dip into their backup reserve or use battery power they need to keep the business running.

Can my client agree set times for UKPN to use their battery?

Yes but the hours need to match the times when UKPN needs help in that particular area.

UKPN calls this arrangement long-term scheduled utilisation. In other words, your client agrees in advance how much less electricity their site will take from the grid, when it will do that and how long the agreement will last.

For example, a winter 2026/27 contract might require the site to take less grid electricity between 5pm and 7pm on weekdays. The battery could supply the site’s equipment during those two hours.

GridVolt’s software checks that your client’s battery can supply the agreed power for the full period and has enough stored electricity for the assignment. Your client doesn’t need the battery to keep reducing grid use for UKPN at other times of the day. It may still need to charge beforehand so it’s ready.

Can my client get paid to keep their battery ready, even if UKPN doesn’t use it?

Yes. Your client could receive a payment for keeping agreed battery power available at times when UKPN may need to use it, such as 5pm to 7pm on weekdays.

UKPN confirms the work it needs the day before. UKPN calls this arrangement their scheduled availability and operational utilisation service.

Your client receives a payment for keeping the agreed battery power ready. If it turns out that UKPN needs to use that battery power, they can also earn a utilisation payment for making the agreed change.

GridVolt won’t enter your client into a trade if it would use up the electricity their battery needs to keep for UKPN.

Can my client offer their battery to UKPN for just one day?

Yes, once the site and equipment have passed UKPN’s checks, GridVolt can offer your client’s battery for particular hours the next day. UKPN calls this day-ahead scheduled utilisation.

For example, UKPN might need businesses in that area to take less electricity from the grid between 5pm and 7pm tomorrow. Your client’s battery could supply more of their equipment’s electricity during those two hours.

Before making an offer, GridVolt checks how much power the battery could provide, for how long and how much stored electricity your client needs to keep for their own use.

In UKPN’s day-ahead auctions, we tell UKPN how much less electricity the site could take from the grid, the hours we can cover and the price we want for the work. If UKPN accepts it, we arrange for the battery to power the client’s equipment during those hours.

How do I know whether my client’s battery is suitable for UKPN flexibility?

Send us the site’s postcode, MPAN and battery and inverter make and model.

We check the site’s network connection against UKPN’s current tender requirements and whether the battery and inverter meet UKPN’s requirements.

Remember that a postcode gives us a starting point, but UKPN still needs to confirm where the site connects to its network. Two nearby businesses may have different connections.

UKPN’s published minimum offer is 10 kW in each zone. With many commercial battery inverters available at 30 kW, 50 kW, 100 kW and more, 10 kW will be achievable for many sites but the key factor is your client’s site must be able to change its grid use by 10 kW when UKPN needs it.

How can I get my client into UKPN flexibility services?

GridVolt can handle the setup, trading and paperwork for your client.

Your client can deal directly with UKPN if they qualify. But this is a complex process that would require them to register their company and equipment on Localflex, complete UKPN’s checks and sign its framework agreement.

They would then need the knowledge and software to make offers to UKPN, arrange the battery’s response and provide the meter data used to check delivery and calculate payments.

If your client would rather leave this work to us, we can handle it as their aggregator. We coordinate their battery with other eligible equipment in the same UKPN zone. This group is called a virtual power plant, or VPP. Their equipment stays at their site. We remotely handle their battery’s charging and discharging and get the site’s meter readings.

Before your client signs up, we confirm who your client contracts with, who submits offers, who supplies the meter data used to check delivery and how your client gets paid. We also confirm any ongoing payments to you based on trades, where agreed with GridVolt.

So, you install the battery, inverter and metering. We supply the controller and support you remotely during commissioning.

How much could my client earn from UKPN flexibility?

Your client will be paid for keeping power ready for the grid, making the agreed change (like using the battery to supply more of the site’s electricity so they take less from the grid), or both.

How much they’ll be paid depends on:

  • The type of trade
  • Where they are located
  • The powered offer
  • The hours their battery is ready to work
  • Payment amount agreed to by UKPN
  • The commissions taken by your company and GridVolt

GridVolt does the measuring using your client’s meter readings, actual tariff and operating limits.

For example, your client might normally save the battery’s charge for an expensive evening period. If we use some of that charge for UKPN earlier and can’t recharge in time, they may have to buy more electricity later. We check whether the UKPN payment would cover that extra cost and leave them better off.

Don’t use a published UKPN rate or budget isn’t an annual income forecast. Ask GridVolt to confirm the service and the estimate’s assumptions before you quote income.

My client is in the UKPN area. What opportunities are there near them?

Here are examples of UKPN’s weekday hours for reducing grid use in winter 2026/27, from our 7 October 2026 database. We check which opportunities are open for your clients on a daily basis and whether your client’s site qualifies.

LocationPublished weekday hours
Willesden, London (Willesden Grid)4pm to 7pm
Bow, London5pm to 8pm
Norwich area (Trowse Grid 33)4:30pm to 6:30pm
Luton (Luton North Grid)3:30pm to 7pm
Enfield (East Enfield)4pm to 6:30pm
Worthing (West Worthing)5pm to 7pm
Bedford and Kempston (Austin Canons Primary)9am to 11am
Harpenden (Central Harpenden)4pm to 7pm
Cockfosters, North London5pm to 7pm
Haverhill10:30am to 1pm
Chatteris4:30pm to 6:30pm
Knebworth5pm to 7pm
Tiptree4:30pm to 6:30pm
Exning, near Newmarket2:30pm to 4:30pm
Mildenhall (Mildenhall Total)4pm to 5:30pm

What documents do you need to sign onto the UKPN flexibility services?

Send GridVolt the client’s site postcode, a recent electricity bill and the battery and inverter make and model. This can be for a battery you’re planning to install or one that’s already running.

For the full assessment, we’ll also need:

  • Twelve months of half-hourly import readings and export readings where available.
  • The current import tariff and export agreement.
  • The proposed or installed battery’s power in kW, usable storage in kWh and any solar capacity.
  • The site’s import and export limits, plus any connection restrictions.
  • The power and stored electricity your client needs to keep for backup or other site uses.

Send the single-line diagram and details of the existing controller and meter if you have them. You don’t need every item before you get in touch.

GridVolt can then assess the equipment and model the savings and confirmed trading options for that site. We’ll send you figures you can use in your proposal, and you keep the installation work and client relationship.